Brief Description
The Computer Validation Installation Qualification (IQ) Protocol is used to confirm that a computerized system has been installed correctly before further validation testing is performed. It ensures that all important hardware and software components are properly installed and that supplier recommendations have been followed. The protocol includes preparation of a signature log, component list, installation sequence, and system diagram. The component list records details such as vendor, model, serial number, operating system, antivirus, memory, and other important system information. The installation sequence is performed in the correct order and supported with documented evidence. The IQ also checks relevant vendor manuals, system configuration, and supporting documents required for system operation and future OQ/PQ testing. The protocol is reviewed and approved by the User Department, Information Technology, Computer Validation, and Quality Assurance to confirm that installation activities are properly completed.

Impact Assessment
The Computer Validation Installation Qualification (IQ) Protocol will have a positive impact on the computer validation process because it confirms that the system is installed correctly before further testing and use. It helps ensure that all important hardware and software components are properly installed and that supplier recommendations are followed.
The protocol checks important documents such as the signature log, component list, installation sequence, system diagram, vendor literature, and system configuration. This improves documentation, traceability, and control of the installed system.
Proper review and approval by the User Department, Information Technology, Computer Validation, and Quality Assurance helps confirm that technical details, SOP compliance, and document completion are properly checked. Overall, this IQ Protocol reduces the risk of incorrect installation, supports smooth OQ/PQ testing, and provides documented evidence that the system installation has been completed properly.
Questions & Answers
Q1. What is the purpose of the Installation Qualification (IQ) Protocol?
Answer: The IQ Protocol confirms that the computerized system has been installed correctly and that all critical components are properly installed.
Q2. What is checked in the component list?
Answer: The component list includes hardware and software details such as vendor, model, serial number, memory, hard drive space, antivirus, domain name, and operating system version.
Q3. What is an installation sequence?
Answer: It is the correct order in which system components are installed according to vendor recommendations, with evidence of important installation steps.
Q4. Why is a system diagram prepared?
Answer: A system diagram is prepared to show how the major components of the computerized system are connected with each other.
Q5. Why is vendor literature required?
Answer: Vendor manuals and literature are required to support proper operation and maintenance of the system.
Q6. What is system configuration documentation used for?
Answer: It is used when required for OQ/PQ testing and for proper system use.
Q7. Who reviews and approves the IQ Protocol?
Answer: The User Department, Information Technology, Computer Validation, and Quality Assurance review and approve the IQ Protocol.
Q8. What happens after IQ activities are completed?
Answer: Final approval is given after confirming that the installation has been completed and the required documents have been reviewed.